KEY PROJECT TASKS:
- Identified five viable options for the client to evaluate
- Developed a weighted decision matrix to assess each alternative’s benefits and limitations to identify key tradeoffs using the following criteria:
- Long-term effectiveness and permanence
- Reduction of toxicity, mobility or volume throughout treatment
- Short-term effectiveness
- Implementability
- Cost
- Decision matrix was developed in strict accordance with guidance documents set forth by the United States Environmental Protection Agency
PROJECT COMPLETION: 2012
PROJECT VALUE: Confidential
SIZE OF SITE: 13.5 acres